Construction Update
Route 9 Ledge Stabilization, Woodford
DATE: Thursday, 5/27/21

TRAFFIC IMPACT:

A lane shift is in effect. Traffic has been reduced from 2 lanes to one lane in the project area for eastbound traffic (traffic heading out of Bennington/Woodford toward Searsburg and Wilmington).


CONSTRUCTION ACTIVITIES:
 
Crews are scheduled to complete hand scaling on the south ledge late next week or early in the week of 6/7. Rock dowels and shear keys are being used to help reinforce the existing ledge and to help prevent further sliding of the ledge in the future.

Holiday: In observance of the Memorial Day holiday, crews will not be working Saturday, 5/29 through Monday, 5/31. Work will resume on Tuesday, 6/1 at 7:00 a.m.
Some of the large boulders removed on Monday.
Crews performing hand-scaling work.
LOCATION: Route 9 just east of Notch Road in Woodford, VT approximately 2.9 miles east of the Bennington-Woodford town line.


PROJECTED COMPLETION: Fall 2022
Contact Information:
Name - Natalie Boyle
Phone - (802) 855-3893
Email - nboyle@eivtech.com
To learn more about VTrans Construction Projects, visit our projects website.